Review Agenda Item
Meeting Date: 8/17/2022 - 3:30 PM
Category: Consent Calendar
Type: Action
Subject: 11.23 BUILDING AND GROUNDS: Ratification of Change Orders No. 23-023 and 23-024 for Bid Category 23 - Pro Craft, Incorporated for the Liberty High School Project (funded through Various Facilities Funds in the amount of $7,696.78, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
ProCraft CO #23-023.pdf
ProCraft CO 23-024.pdf
Summary: The Board of Trustees previously approved, and the District has undertaken the facilities project known as the Liberty High School Project, which consists of constructing a new high school facility. On March 20, 2019, the Board of Trustees approved the contract with Pro-Craft Construction, Inc. ("Pro-Craft") in the amount of $4,470,000 for all services related to site plumbing on the Liberty High School Campus. During the completion of Pro-Craft's scope of work, some changes became necessary due to site conditions and direction from Eastern Municipal Water District (EMWD). Change Order #23-023 was necessary due to the relocation of a fire hydrant at the direction of the EMWD Reclaimed Water Inspector. The fire hydrant's planned location was deemed too close to a domestic water line. Change Order #23-024 was a result of moving a storm drain line that was in conflict with the location of the flagpole in front of the administrative building. These changes resulted in Change Orders #23-023 in the amount of $4,929.38 and Change Order #23-024 in the amount of $2,767.40; for a total cost of $7,696.78.

This is being brought before the Board as ratification due to the need to mitigate schedule impacts on the Liberty High School Project.
Funding: The cost for this item is included in the 2022-23 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees ratify Change Order No. 23-023 and 23-024 for Bid Category 23 - Pro Craft, Incorporated for the Liberty High School Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Sylvia Hinojosa - Director - Purchasing
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member Dr. Jose Luis Araux Moved, Member Dr. Randall Freeman seconded to approve the Original motion 'It is recommended that the Board of Trustees ratify Change Order No. 23-023 and 23-024 for Bid Category 23 - Pro Craft, Incorporated for the Liberty High School Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   