Subject: 13.7 BUILDING AND GROUNDS: Change Order No. 1 for TYR, Incorporated for Inspector of Record Services for the Liberty High School Project (funded through Various Facilities Funds in the amount of $436,096.56, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
TYR - Perris Liberty - Proposal Increase R1.pdf
Summary: The Board of Trustees previously approved and the District has undertaken the facilities project known as the “Liberty High School Project,” which consists of the construction of a new high school facility.

During its January 16, 2019 meeting, the Board approved the contract with TYR, Incorporated in the amount of $914,026.56 for DSA Inspector of Record (IOR) services required by the Division of State Architects Office (DSA) as part of the Liberty High School Project. The original approved proposal included 2 project inspectors - a Main Project Inspector and an Assistant Inspector, as originally required by DSA. In June of 2019, DSA notified the project team and requested an additional Assistant Inspector due to the size, complexity, and scope of the Liberty High School Project. This additional inspector has increased the scope and amount of the original budget which was originally approved for IOR Services by $436,096 through the completion of the project. Additionally, this amount includes a $40,000 contingency to be utilized for additional hours as necessitated by the project schedule or DSA direction. The District recommends the approval of Change Order No. 1 with TYR, Incorporated for IOR Services in the amount of $436,096.
Funding: The cost for this item is included in the 2020-21 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees approve Change Order No. 1 for TYR, Incorporated for Inspector of Record Services for the Liberty High School Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Dawn Bray - Director - Purchasing
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member David Nelissen Moved, Member Anthony T. Stafford, Sr. seconded to approve the Original motion 'It is recommended that the Board of Trustees approve Change Order No. 1 for TYR, Incorporated for Inspector of Record Services for the Liberty High School Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 4 Nay: 0.
The motion Carried 4 - 0
   