Subject: 9.16 BUILDING AND GROUNDS: Ratification of Change Order No. 01 With Cardinal Environmental Consultants, Incorporated for Hazardous Material Management for the Perris High School Completion Phase, Increment 2 Project (funded through Various Facilities Funds in the amount of $4,887, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
Cardinal Inv#21-028 Increment II HazMat CO#1.pdf
Summary: On May 20, 2020, the Perris Union High School District (PUHSD) Board of Trustees approved the Agreement for Hazardous Material Management Services with Cardinal Environmental Consultants, Inc. (Cardinal) for the Perris High School Completion Phase, Increment 2 Project. Cardinal’s services are necessary to comply with all applicable regulations related to the monitoring and abatement of asbestos and any hazardous materials which may be identified during the demolition of the existing original buildings at Perris High School. The original cost for these services is $21,600. During the demolition activities, hazardous materials in the form of asbestos-containing materials in excess of the additional scope of services were encountered in the demolition area. The abatement of these additional materials, the creation of the additional reports, and the additional services by Cardinal resulted in Change Order No. 01 in the amount of $4,887, which revises the contract amount to $26,487.

This is being brought forward as ratification due to the project schedule timelines. The work needed to be performed before demolition of the buildings could start.
Funding: The cost for this item is included in the 2021-22 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees ratify Change Order No. 01 with Cardinal Environmental Consultants, Incorporated for Hazardous Material Management for the Perris High School Completion Phase, Increment 2 Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Dawn Bray - Director - Purchasing
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member David Nelissen Moved, Member Dr. Randall Freeman seconded to approve the Original motion 'It is recommended that the Board of Trustees ratify Change Order No. 01 with Cardinal Environmental Consultants, Incorporated for Hazardous Material Management for the Perris High School Completion Phase, Increment 2 Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Dr. Randall Freeman     Yes
Elizabeth Vallejo     Yes
Anthony T. Stafford, Sr.     Yes
David Nelissen     Yes
Dr. Jose Luis Araux     Yes