Subject: 12.7 BUILDING AND GROUNDS: Ratification of Agreement and Change Order No. 001 With Greer’s Contracting & Concrete, Incorporated for the Heritage High School Grounds Yard Concrete and Fencing Project (funded through Various Facilities Funds in the amount of $20,900, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
Greer's Contracting and concrete_HHS_FE_21-22.pdf
Greer Change Order.pdf
Summary: On May 19, 2021, the PUHSD Board of Trustees awarded the construction contracts to begin the Heritage High School Aquatics and Team Room Project (Project). In order to begin this project, four (4) 40-foot storage containers and the fencing that makes up the Heritage Grounds Yard had to be relocated along with fencing and gates that make up the yard. On June 30, 2021, the District requested proposals and awarded the project to Greer’s Construction & Concrete, Inc. This project includes the installation of concrete to make up the Grounds Yard in a new location on campus, the relocation of fencing around the yard, along with related grading and site work to create the new yard. This work was completed by Greer’s Construction & Concrete ​in the amount of $19,000.

During the construction of the new yard, it was determined that additional fencing and site work was required to fully enclose the yard in a secure manner. This resulted in Change Order No. 001 in the amount of $1,900.

This Agreement is being brought forth as ratification due to the need to move the Grounds Yard and storage containers out of the way of the new Heritage Aquatic Facility footprint in a timely manner. Ratification of this Agreement helped mitigate any potential impacts to the project schedule.
Funding: The cost for this item is included in the 2021-22 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees ratify the Agreement and Change Order No. 001 with Greer’s Construction & Concrete, Incorporated for the Heritage High School Grounds Yard Concrete and Fencing Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Dawn Bray - Director - Purchasing
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member Dr. Randall Freeman Moved, Member David Nelissen seconded to approve the Original motion 'It is recommended that the Board of Trustees ratify the Agreement and Change Order No. 001 with Greer’s Construction & Concrete, Incorporated for the Heritage High School Grounds Yard Concrete and Fencing Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Dr. Jose Luis Araux     Yes
David Nelissen     Yes
Anthony T. Stafford, Sr.     Yes
Dr. Randall Freeman     Yes