|
|
|
|
|
|
Meeting Date:
|
10/16/2024 - 2:00 PM
|
Category:
|
Action Items
|
Type:
|
Action
|
Subject:
|
14.10 BUILDING AND GROUNDS: Award of Bid #100224 - Liberty High School Modular Site Work Project - Phase 2 (funded through Various Facilities Funds in the amount of $764,950, not the General Fund)
|
Strategic Plan:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On August 23, 2024, the Perris Union High School District (“The District”) issued a formal Notice Inviting Bids for the Liberty High School Modular Site Work Project - Phase 2 (“The Project”). This project includes the site work and utility connections necessary for eight (8) portables to be installed at Liberty High School. The bid opening was held on October 2, 2024. Responsive Bids were submitted as follows:
CONTRACTOR / BASE BID
R Dependable Construction, Inc. / $764,950
Roadway Engineering & Construction / $934.400
Bogh Engineering / $1,042,770
ABNY General Engineering, Inc. / $1,207,000
Inland Building Construction Companies, Inc. / $1,334,000
Cornerstone Construction Service, Inc. / $1,338,000
R. Jensen Co., Inc. / $1,399,777
Epsilon Engineering, Inc. / $1,444,690
Blackstone Builders, Inc. / $1,540,759
MLC Constructors / $1,554,241
The bid documents of the apparent low bidder were reviewed and a post interview was conducted with said bidder. Pursuant to Public Contract Code 20111, the District is recommending the award of contract to the lowest responsive and responsible bidder, R Dependable Construction, Inc.
|
Funding:
|
The cost for this item is included in the 2024-25 operating budget funded through Various Facilities Funds, not the General Fund.
|
Recommendation:
|
It is recommended that the Board of Trustees award Bid #100224 - Liberty High School Modular Site Work Project - Phase 2.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Hector Gonzalez - Director of Facilities
|
|
Signed By:
|
|
Sylvia Hinojosa - Director - Purchasing
|
|
Signed By:
|
|
Candace Reines - Deputy Superintendent
|
|
Signed By:
|
|
Dr. Jose Luis Araux - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Steve Campos Moved, Member David Nelissen seconded to approve the Original motion 'It is recommended that the Board of Trustees award Bid #100224 - Liberty High School Modular Site Work Project - Phase 2.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | David Nelissen | Yes | Anthony T. Stafford, Sr. | Yes | Edward Garcia, Jr. | Yes | Elizabeth Vallejo | Yes | Steve Campos | Yes | |
|
|
|
|
|
|