Review Agenda Item
Meeting Date: 11/16/2022 - 3:30 PM
Category: Consent Calendar
Type: Action
Subject: 11.11 BUILDING AND GROUNDS: Ratification of Change Order #03d-009 for Bid Category 03d - Alcorn Fence Company for the Liberty High School Project (funded through Various Facilities Funds in the amount of $15,582.15, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
Alcorn Change Order #03d-009, $15,582.15 .pdf
Summary: The Board of Trustees previously approved, and the District has undertaken the facilities project known as the Liberty High School Project, which consists of the construction of a new high school facility. On March 20, 2019, the Board of Trustees awarded the contract to Alcorn Fence Company (Alcorn) in the amount of $3,130,715, for all services related to site fencing and gates on the Liberty High School Campus. During the completion of Alcorn’s scope of work, changes to Alcorn Fence’s scope of work became necessary. Change Order #03d-009 combines and reconciles all change orders for Category 03d - Fencing; this includes the final change event #03d-010, which became necessary to redesign the fencing around the main gas valve and meter. This change was due to a redesign by The Southern California Gas Company which increased the distance between the gas equipment and the perimeter fencing of the enclosure. The cost of this Change Order #03d-009 is $15,582.15.

This is being brought before the Board as ratification due to the need to mitigate schedule impacts to the Liberty High School Project.
Funding: The cost for this item is included in the 2022-23 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees ratify Change Order #03d-009 for Bid Category 03d - Alcorn Fence Company for the Liberty High School Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Sylvia Hinojosa - Director - Purchasing
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member Dr. Jose Luis Araux Moved, Member Anthony T. Stafford, Sr. seconded to approve the Original motion 'It is recommended that the Board of Trustees ratify Change Order #03d-009 for Bid Category 03d - Alcorn Fence Company for the Liberty High School Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
Elizabeth Vallejo     Yes
Anthony T. Stafford, Sr.     Yes
Dr. Randall Freeman     Yes
Dr. Jose Luis Araux     Yes
David Nelissen     Yes