11.12 BUILDING AND GROUNDS: Ratification of Change Order No. 001 With IVL Contractors, Incorporated for the California Military Institute, Gymnasium and Parking/Circulation Project (funded through Various Facilities Funds in the amount of $16,106.60, not the General Fund)
|
Strategic Plan:
|
|
Enclosure
|
|
File Attachment:
|
|
Summary:
|
On August 18, 2021, the Board of Trustees approved a contract for $81,500 with IVL Contractors, Inc. (IVL). IVL was hired to move seven (7) portables at the California Military Institute as part of the Gym and Parking/Circulation Project. During IVL’s completion of their scope of work, it became necessary to cancel IVL’s scheduled date to move the portables due to unforeseen site conditions. This resulted in IVL having to reschedule and remobilize their crews to complete their scope of work. Additionally, IVL was required to work overtime to complete the portable move before students returned to CMI on August 4. This remobilization and overtime resulted in Change Order No. 001 in the amount of $16,106.60. This is being brought before the Board as ratification due to the need to mitigate schedule impacts related to completing the movement of seven (7) portables during CMI’s Gym and Parking/Circulation Project.
|
Funding:
|
The cost for this item was included in the 2021-22 operating budget funded through Various Facilities Funds, not the General Fund.
|
Recommendation:
|
It is recommended that the Board of Trustees ratify Change Order No. 001 with IVL Contractors, Incorporated for the California Military Institute, Gymnasium and Parking/Circulation Project.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Hector Gonzalez - Director of Facilities
|
|
Signed By:
|
|
Sylvia Hinojosa - Director - Purchasing
|
|
Signed By:
|
|
Candace Reines - Deputy Superintendent
|
|
Signed By:
|
|
Grant Bennett - Superintendent
|
|
|
|
Vote Results:
|
Original Motion | Member Dr. Jose Luis Araux Moved, Member Dr. Randall Freeman seconded to approve the Original motion 'It is recommended that the Board of Trustees ratify Change Order No. 001 with IVL Contractors, Incorporated for the California Military Institute, Gymnasium and Parking/Circulation Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0. | The motion Carried 5 - 0 | | | Elizabeth Vallejo | Yes | Dr. Randall Freeman | Yes | Dr. Jose Luis Araux | Yes | Anthony T. Stafford, Sr. | Yes | David Nelissen | Yes | |
|
|
|
|
|
|