Subject: 11.10 BUILDING AND GROUNDS: Ratification of Change Order No. 23-025 for Bid Category 23 - Pro-Craft Construction, Incorporated for the Liberty High School Project (funded through Various Facilities Funds in the amount of $2,677.72, not the General Fund)
Strategic Plan:
Enclosure
File Attachment:
Pro Craft 23-025 CO.pdf
Summary: The Board of Trustees previously approved, and the District has undertaken the facilities project known as the Liberty High School Project, which consists of constructing a new high school facility. On March 20, 2019, the Board of Trustees awarded the contract to Pro-Craft Construction, Inc. (“Pro-Craft”) in the amount of $4,470,000 for all services related to site plumbing on the Liberty High School Campus. During the completion of Pro-Craft’s scope of work, repair to a damaged storm lateral drain line became necessary. This damage occurred during the course of constructing the campus and was not attributable to a specific event that damaged the line. The District requested the repair by Pro-Craft take place immediately to mitigate delays and to complete work in the area of the broken lateral storm drain line. The cost of this repair was $2,677.72

This is being brought before the Board as ratification due to the need to mitigate schedule impacts to the Liberty High School Project.
Funding: The cost for this item is included in the 2022-23 operating budget funded through Various Facilities Funds, not the General Fund.
Recommendation: It is recommended that the Board of Trustees ratify Change Order No. 23-025 for Bid Category 23 - Pro-Craft, Incorporated for the Liberty High School Project.
Approvals:
Recommended By:
Signed By:
Hector Gonzalez - Director of Facilities
Signed By:
Sylvia Hinojosa - Director - Purchasing
Signed By:
Candace Reines - Deputy Superintendent
Signed By:
Grant Bennett - Superintendent
Vote Results:

Original Motion
Member Dr. Jose Luis Araux Moved, Member Anthony T. Stafford, Sr. seconded to approve the Original motion 'It is recommended that the Board of Trustees ratify Change Order No. 23-025 for Bid Category 23 - Pro-Craft, Incorporated for the Liberty High School Project.'. Upon a Roll-Call Vote being taken, the vote was: Aye: 5 Nay: 0.
The motion Carried 5 - 0
   
David Nelissen     Yes
Dr. Jose Luis Araux     Yes
Dr. Randall Freeman     Yes
Anthony T. Stafford, Sr.     Yes